6 days agoHospitals with unsafe concrete expected to miss rebuild deadline
Work to fix hospitals built using unsafe concrete will not be completed in time to meet the government's target, a new report has warned. Seven hospitals built using Raac, or reinforced autoclaved aerated concrete, were prioritised for remedial work last year, with the government setting a deadline of 2030. The new buildings are now expected to open in 2032 and 2033 - but some are already facing pressure to meet the revised timetable, the National Audit Office (NAO) said.