"With inflation, the further you push out the start date of the project, the more expensive it becomes. Those higher ranges - where you're going up to €6bn and over - they're for if the project is delayed for 10 years before it starts."
"It isn't the children's hospital. It's not redesigning the wheel. It's just a really long version of what we've done before. We'll probably split the pipeline contracts into four or five contracts, and keep them moving at the same time."