A gas main reinforcement project on Highbridge Road commenced on July 7 and will last until October 31, under a temporary traffic order from Barking and Dagenham Council. The project consists of nine phases, with various road closures and traffic restrictions in place throughout. Highbridge Road will experience closures impacting pedestrians and vehicles, including banned turns for HGVs and buses. Alternative routes will be signed during the project, which has a traffic order effective for 18 months, allowing for further works if needed.
The project will reinforce a gas main for redevelopment, organized in nine phases with various road closures and restrictions, affecting Highbridge Road.
This project includes restrictions on waiting and loading, and closures for pedestrians and vehicles along sections of Highbridge and surrounding roads.