Decision to rebuild end of Santa Cruz Wharf slated for April
Briefly

The city manager emphasized the significance of the December 23 incident, noting, "On Dec. 23 our municipal wharf sustained major damage due to one of the strongest west swell and high surf events that we've experienced on record." This highlights the severity of the situation and sets the stage for the urgency of recovery efforts.
Parks and Recreation Director Tony Elliot outlined the immediate recovery efforts, including the necessity to locate the sunken crane and assess the structural integrity before reopening. He mentioned, "Two critical things needed to happen before the Wharf could be reopened: locating the crane and other heavy equipment that sank to the ocean floor using sonar, and having an engineer assess the structure." This reflects the complex, multifaceted approach required for recovery.