West Sussex County Council has planned to allocate up to £25 million from the sale of capital assets to support a significant Oracle-based transformation project. Initially estimated at £2.6 million, costs have soared to around £40 million amid project delays and contract renegotiations with Oracle. The project, originally set to launch in 2021, has now faced multiple postponements, delaying expected implementation until December 2025. The council is leveraging the flexible use of capital receipts scheme to finance this high-cost initiative, with a revised contract now stretching to June 2028.
West Sussex County Council will utilize up to £25 million from asset sales to fund an Oracle-based transformation project, massively exceeding initial budget estimates.
The project costs ballooned from an estimated £2.6 million to around £40 million due to unexpected delays and contract renegotiations with Oracle.