Water supply repairs for Greater Dublin Area started on August Bank Holiday, chosen for low demand. Five leaks are being fixed in a major pipeline project. Operations require isolating the water supply for 28 hours, involving the removal of 35 meters of pipe to install a new section. Over a thousand personnel are engaged, with strategic management of water storage levels to ensure sufficient supply during repairs. Customers are advised to limit water usage to aid repair efforts.
The large-scale operation involves the removal of 35 metres of pipeline to allow for the installation of a new section of pipe.
More than a thousand people have been involved at various different stages over the past few weeks.
We have also carefully cut the damaged section of pipeline and the cranes have removed these pieces.
Small actions can help maintain everyone's water supply during the critical repair works.
Collection
[
|
...
]