Massachusetts ratepayers to pay extra $512 million for transmission line for Canadian hydropower
Briefly

Even with these unanticipated costs, this is clean energy at a pretty good price. I'm not sure we'll be at prices this low in the future.
The project's cost grew from $1 billion to at least $1.5 billion because of inflation and delays caused by opponents.
Supporters of the project say the 1,200 megawatts of electricity it provides would lower electric rates across the region, reduce carbon pollution.
Developers previously said they expect the project to be completed by late next year, but there are provisions for pushing the completion date further back.