Piccadilly line's new 3.4bn trains hit another delay as testing slips
Briefly

Piccadilly line's new 3.4bn trains hit another delay as testing slips
"Ahead of any new train being introduced into an underground railway, a lot of remedial work has to be carried out to ensure the new trains don't interfere with often decades-old tunnel cabling and signalling equipment. The existing signalling system is being modified to ensure compatibility with the new trains, including repositioning lineside signals and installing additional signal indicators to ensure visibility from the longer trains."
"Works are also being carried out at various power sub-stations and to trackside cabling to upgrade power system capacity. As part of line-wide infrastructure clearance and gauging works, targeted adjustments are being made to ensure trains can safely travel through stations. New platform infrastructure is also being installed, such as platform end barriers and a new digital platform CCTV camera system."
"However, it's taking longer than planned to carry out the work, which TfL puts down to limited engineering time and the condition of the existing equipment being worse than expected. Some of those delays are now affecting the ability to run the new trains in tests along the Piccadilly line, which is why they are pushing the date for first passenger services back by another six months."
The Piccadilly line's new train fleet of 94 trains faces another significant delay, now expected in the first half of 2027 instead of late 2025 or mid-2026. The project cost has increased to £3.4 billion. Extensive remedial work is required to ensure compatibility with decades-old tunnel infrastructure, including modifications to signalling systems, power sub-stations, and trackside cabling. Platform infrastructure upgrades include new barriers and digital CCTV systems. Limited engineering time and worse-than-expected equipment conditions have extended the timeline. Testing delays on the Piccadilly line have pushed passenger service introduction back by six months, though service by December 2026 remains possible.
Read at ianVisits
Unable to calculate read time
[
|
]