An Bord Pleanála requested details from Amazon Web Services about the environmental implications of three proposed data centers as part of an appeal process initiated over 18 months ago. This request is in light of the recently published Climate Action Plan 2025 and a report on Ireland's Greenhouse Gas Emissions. The board aims to confirm findings from AWS's initial Environmental Impact Assessment and ensure capacity in the national grid to support the development. AWS must respond by May 29.
An Bord Pleanála has sought clarification from AWS regarding the environmental impact of three planned data centers, referencing the recent Climate Action Plan 2025.
The appeals board requires AWS to affirm findings from its previous Environmental Impact Assessment in light of new climate reports published post-application.