CF: Detailed timeline emerges for new stadium construction and San Siro demolition
Briefly

CF: Detailed timeline emerges for new stadium construction and San Siro demolition
"Construction of urbanisation works - from August 2027 to January 2030 (29 months) Construction of the new Milan stadium - from October 2027 to October 2030 (36 months) Final testing - January 2030 to December 2030 (11 months) INAUGURATION OF THE NEW MILAN STADIUM - December 2030 Public tender for the demolition of the Meazza stadium - from October 2030 to March 2031 (5 months)"
"Preparation and submission of the detailed urban planning proposal for Phase 2 - from July 2027 to January 2028 (6 months) Approval of the detailed urban planning project for phase 2 - from January 2028 to December 2030 (36 months) Preparation and submission of the Final Project to the competent authorities - from January 2031 to July 2031 (7 months) Approval of the final project, signing of the agreement and issuing of the permits - from August 2031 to February 2032"
AC Milan and Inter have established a phased roadmap for San Siro redevelopment. Phase 1 begins with urbanisation works from August 2027, followed by construction of a new stadium from October 2027 to October 2030, final testing through December 2030, and inauguration in December 2030. A public tender for Meazza demolition runs October 2030–March 2031, with demolition and partial conservation from April 2031 to May 2032. Phase 2 covers preparation, approvals and final project submissions from 2027 through early 2032, with executive design and further works to follow, extending the overall timeline toward 2036.
Read at SempreMilan
Unable to calculate read time
[
|
]