Bromley housing scheme subcontractor 'illegally removed electrics from site'
Briefly

The delays in construction were exacerbated by the discovery of underground air raid shelters, further complicating the housing project for the Bromley Council.
Council officers indicated that the total estimated cost for the housing scheme ballooned to 15.8 million due to unforeseen damages and the need for additional funding.
A council officer highlighted that several subcontractors were allegedly not paid, resulting in a situation where one subcontractor was caught illegally removing goods from the site.
Conservative Councillor Colin Smith expressed the council's commitment to pursue maximum refunds for the damages caused due to the project's complications and contractor issues.